2019
Usharam Integra Site Construction – 3 CELLAR + G+3 COMMERCIAL + 10 FLOORS RESIDENTIAL FLOORS COMPLETED (15.08.2019)
STRUCTURE WORK COMPLETED. (01.03.2019)
2018
6TH AND 9TH FLOOR PLASTERING WORK IN PROGRESS. (09-11-2018)
STRUCTURE WORK COMPLETED. (09-11-2018)
BRICK WORK IN PROGRESS. (09-11-2018)
STRUCTURE WORK COMPLETED, 6TH FLOOR BRICK WORK UNDER PROGRESS. (10-08-2018)
9TH FLOOR RESIDENTIAL SLAB UNDER PROGRESS, 4TH FLOOR SLAB BRICK WORK UNDER PROGRESS. (24-05-2018)
6TH FLOOR SLAB COMPLETED. (26-02-2018)
5TH FLOOR SLAB COMPLETED. (12-01-2018)
2017
3 CELLER, GROUND & FIRST FLOOR SLAB COMPLETED. 2ND FLOOR SLAB UNDER PROGRESS. (14-JULY-2017)
3 CELLER PARKING AND GROUND FLOOR COMPLETED AND FIRST FLOOR SLAB IN PROGRESS (16-MAY-2017)