Usharam Integra

2019
15/08/2019

Usharam Integra Site Construction – 3 CELLAR + G+3 COMMERCIAL + 10 FLOORS RESIDENTIAL FLOORS COMPLETED (15.08.2019)

    01/03/2019

    STRUCTURE WORK COMPLETED. (01.03.2019)

      2018
      09/11/2018

      6TH AND 9TH FLOOR PLASTERING WORK IN PROGRESS. (09-11-2018)

        09/11/2018

        STRUCTURE WORK COMPLETED. (09-11-2018)

          09/11/2018

          BRICK WORK IN PROGRESS. (09-11-2018)

            10/08/2018

            STRUCTURE WORK COMPLETED, 6TH FLOOR BRICK WORK UNDER PROGRESS. (10-08-2018)

              24/05/2018

              9TH FLOOR RESIDENTIAL SLAB UNDER PROGRESS, 4TH FLOOR SLAB BRICK WORK UNDER PROGRESS. (24-05-2018)

                26/02/2018

                6TH FLOOR SLAB COMPLETED. (26-02-2018)

                  12/01/2018

                  5TH FLOOR SLAB COMPLETED. (12-01-2018)

                    2017
                    17/09/2017

                    17-OCT-2017

                      14/07/2017

                      3 CELLER, GROUND & FIRST FLOOR SLAB COMPLETED. 2ND FLOOR SLAB UNDER PROGRESS. (14-JULY-2017)

                        16/05/2017

                        3 CELLER PARKING AND GROUND FLOOR COMPLETED AND FIRST FLOOR SLAB IN PROGRESS (16-MAY-2017)

                          07/01/2017

                          07-JAN-2017